2-Day Look ahead

  • Installation of components at Turbine 10, 16 & 54.
  • Mechanical completion crew at Turbine 9.
  • Pre-assembly work at Turbine 41.
  • Grid terminations at Turbine 1.
  • Drain tile repair at Turbine 4.
  • Rock removal at Turbine 48.
  • Grid cable pull at Turbine 5.
  • PD testing on Circuit 3.

THIS WEEK: Construction Activities October 19th - October 25th

  • Installation of components at Turbines 10, 32, 12, 54, 16, 21 & 20.
  • Mechanical completion crew at Turbines 9 & 1.
  • Pre-assembly work at Turbines 41, 35 & 32.
  • Intersection improvement reclamation.
  • Grid terminations at Turbines 1 & 5.
  • Mobilization of crane at Turbine 12.
  • Fiber splicing in various locations.
  • Grid cable pull at Turbines 5 & 6.
  • VLF testing on Circuit 1.
  • PD testing on Circuit 3.

Next Week: Construction Activities October 26th - November 1st

  • Installation work at Turbines 12, 54, 16, 20 & 21.
  • Pre-assembly work at Turbines 41, 35 & 32.
  • Road entrance reclamation at Turbine 11.
  • Pre-assembly at Turbines 23 & 41.
  • Fiber splicing in various locations.
  • Grid cable pull at Turbine 6.
  • MCC at Turbine 1.
  • PD testing.