  • Site grading and excavation at project substation off of County Road 13.
  • Increased traffic in and out of substation area and laydown yard.
  • Site grading at laydown yard on Forgues Rd.
  • Construction office trailers to arrive in laydown yard on Forgues Rd.
  • Further surveys and staking on private properties and public ROW.
  • Access road entrance at T-06, T-01 & T-02.
  • Stripping of access roads.

THIS WEEK: June 17-23, 2019

The following items are scheduled for this week.

  • Site grading and excavation at project substation off of County Road 13.
  • Delivery, testing and installing micro piles at substation.
  • Further surveys and staking on private properties and public ROW.
  • Site grading, preparation and gravel delivery at laydown yard on Forgues Rd.
  • Begin access road entrances at T-06.
  • Equipment arriving at laydown yard on Forgues Rd.
  • Stripping access roads.
  • Arrival of construction trailers to laydown yard on Forgues Rd.

Next Week: June 24-30, 2019

  • Foundation preparation at project substation off of County Road 13.
  • Gravel installation at laydown yard on Forgues Rd and potential delivery of construction equipment and trailers.
  • Further surveys and staking on private properties and public ROW.
  • Continue access road entrances and stripping of access roads.