Nation Rise Wind Farm Construction Updates

Please note dates are planned and may change. Changes will be reflected in the next day update.

If you have any questions or comments, please contact the following:

Email: nationrise@edpr.com     Phone: (613) 240-0348

Published: Sunday, December 8, 2019 at 9:30AM

 

2-Day Look ahead

Activities anticipated to be completed over the next two days:

THIS WEEK: December 9th - December 13th

The following items scheduled for this week:

Next Week: December 16th - December 20th

The following items scheduled for next week:

 

Activity Map

(Click Image to Enlarge)

Delivery Map

The delivery routes to be utilized in the upcoming week are found on the map below. These deliveries can include turbine tower sections, turbine blades, turbine nacelles and other supporting infrastructure. These deliveries will be escorted by the transportation company. We ask for patience from the public when delivering these components.

(Click Image to Enlarge)

Contact sheet