On May 13th, 2020 the Ontario Divisional Court provided its decision regarding the project’s application for judicial review, quashing the decision of the Minister of Environment, Conservation and Parks’ decision to purportedly revoke the project’s Renewable Energy Approval. EDPR is in the process of thoroughly reviewing the Court’s decision to assess implications and next steps for the project. Given the Court’s decision, EDPR is eager to recommence construction of the Nation Rise Wind Farm and bring much needed jobs and investment to the community. However, we will provide further updates on next steps to stakeholders as we conclude our review of the Court’s ruling. The Divisional Court’s judgment is publicly available from the Court’s website: https://www.ontariocourts.ca/scj/decisions/

If you have any questions or comments, please contact the following:

Email: nationrise@edpr.com     Phone: (613) 240-0348

 

2-Day Look ahead

  • Maintenance/Retrofit at Turbines 1 & 5
  • Drain tile repairs at Turbines 27 & 52
  • Directional drilling at Nation River
  • Reclamation of work platforms at Turbines 2, 4 & 6
  • Installation of bird mitigation at Substation
  • Installation of grounding on fence & sound wall at Substation
  • Trenching clean up on Concession 1-2

THIS WEEK: Construction Activities

  • Substation maintenance
  • Fiber splicing at Turbines 2 & 6
  • Maintenance/Retrofit at Turbines 1 & 6
  • Fiber Jetting at various locations
  • Drain tile repairs at Turbines 27 & 52
  • Reclamation on temporary conventional roads
  • Directional drilling at Nation River
  • Reclamation of work platforms at Turbines 2, 4 & 6

Next Week: Look Ahead

  • Directional Drilling
  • Reclamation along Access Roads
  • Reclamation at Turbines 5 & 6
  • Repairs at Turbines 4 & 6
  • Trenching clean up on Concession 1-2

 