Nation Rise Wind Farm Construction Updates

Below you will find the anticipated construction activities taking place at Nation Rise Wind Farm in the township of North Stormont. These activities may change based on the needs of the project. Additional activities may also be included at any time. You are welcome to call or e-mail EDPR if you have any questions or comments.

2-Day Look ahead

  • Reclamation activities ongoing at various locations. Remaining reclamation locations include: T25, T27, T29, T32, T35, T44, T41, T48, T52, T56 & T57.

THIS WEEK: Construction Activities August 9th - August 15th

  • Reclamation activities ongoing at various locations. Remaining reclamation locations include: T25, T27, T29, T32, T35, T44, T41, T48, T52, T56 & T57.

Next Week: Construction Activities August 16th - August 22nd

  • Reclamation activities to continue. These activities include the removal of temporary infrastructure such as temporary access roads that were required for construction of the project. Reclamation locations include: T25, T27, T29, T32, T35, T44, T41, T48, T52, T56 & T57.

Activity Map

(Click Image to Enlarge)

Delivery Map

Component deliveries have been completed.

(Click Image to Enlarge)

Contact sheet